Monday, March 20, 2017, Dominion East Ohio Gas Pipeline Infrastructure Repairs 1201
W. 100 & Zimmer
(City of Cleveland Ward 5)

Traffic revision begins March 20, 2017 and remains in effect through October, 2017

Expect additional traffic notices as work progresses

CLEVELAND – Pipeline infrastructure improvements begin on Monday, March 20, 2017, weather permitting, and include work on the following streets:

  • W. 101 from Madison Ave. to Western Ave.
  • W. 100 from Madison Ave. to Western Ave.
  • W. 99 from Madison to Marietta
  • W. 98 from Madison to N. Marginal Dr.
  • From W. 100 to W. 98 on the following streets (Marietta, Cudell, Zimmer, Macon, Gambier, and Nicholas)

Improvement to infrastructure begins with the replacement of old steel mainlines. One lane of traffic will be maintained at all times with traffic control personnel in the work zone directing traffic. Access to adjacent driveways will be maintained and the work will take place during daytime hours (7:00 a.m. to 5:00 p.m.).

This project is scheduled for completion by October 2017.

Contact Dennis Scheid - Hill International at 216-701-2319 with questions/comments.

Editor’s Note: Road construction invariably presents hazards to the public. All travelers are urged to use caution in construction zones. Public safety and the safety of workers is a top priority.

About the City of Cleveland

The City of Cleveland is committed to improving quality of life its residents by strengthening neighborhoods, delivering superior services, embracing diversity and making Cleveland a desirable, safe city in which to live, work and play. For more information on the City of Cleveland, visit online at www.city.cleveland.oh.us, Twitter at @cityofcleveland or Facebook at www.facebook.com/cityofcleveland

-30-